Ocean Star
Ocean Star is a building project in Mina Rashid, Dubai, by Mina Rashid Properties. The Dubai Land Department's register puts it at 30.46% complete, with planned completion on Jul 31, 2025.
Planned completion was Jul 31, 2025. Time since: 1 year 3 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3010), which also shows the latest inspection date and photos.
Facts
- Status
- Past planned completion
- Official progress
- 30.46%, as published by the Dubai Land Department
- Planned completion
- Jul 31, 2025
- Construction start
- Jul 6, 2024
- Units
- 155
- Buildings
- 2
- Developer
- Mina Rashid Properties
- Community
- Mina Rashid, in DLD's area Madinat Dubai Almelaheyah
- Escrow bank
- First Abu Dhabi Bank
- DLD project number
- 3010
The register describes it as: "Shared: B+G ; Building 1: Part (4F+R) & Part (6F+R), Building 2: Part (4F+R) & Part (6F+R) + Entertainment area and Common Facilities at 1st Floor)"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 30.46% | Jul 31, 2025 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
170 off-plan sales in Ocean Star have been registered with the Dubai Land Department, worth AED 417 million in all, the first on May 30, 2024 and the latest on Sep 8, 2026. 1 of them in the last 90 days. The median price over the last 12 months was AED 23,853 per square meter (AED 2,216 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Mina Rashid
- Marina Views Mina Rashid · Mina Rashid 7.09%Planned completion Dec 31, 2028
- Clearpoint Mina Rashid · Mina Rashid 45.05%No planned date in the register
- Seascape Mina Rashid · Mina Rashid 79.13%Planned completion Nov 30, 2026
- Baystar by VIDA Mina Rashid · Mina Rashid 6.3%Planned completion Dec 31, 2029
- Ocean Cove Mina Rashid · Mina Rashid 17.93%Planned completion Aug 31, 2028
- Ocean Point Mina Rashid · Mina Rashid 26.95%No planned date in the register
More by Mina Rashid
- Sera 1 Mina Rashid · Mina Rashid 0.04%Planned completion Nov 30, 2029
- Fior 1 Mina Rashid · Mina Rashid 0%Planned completion Jul 31, 2030
- Sera 2 Mina Rashid · Mina Rashid 0.04%Planned completion Nov 30, 2029
- Marina Place 2 Mina Rashid · Mina Rashid 1.52%Planned completion Dec 31, 2028
- Aurea Mina Rashid · Mina Rashid 0.22%Planned completion Jun 30, 2030
- Avonlea Mina Rashid · Mina Rashid 63.71%No planned date in the register