32.85%complete

Rome 2 by SD

Rome 2 by SD is a building project in Mohammed Bin Rashid Al Maktoum District 11, Dubai, by Samana Star Real Estate Development. The Dubai Land Department's register puts it at 32.85% complete, with planned completion on Jun 30, 2027.

Planned completion: Jun 30, 2027. Time left: 8 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3329), which also shows the latest inspection date and photos.

Facts

Status
Under construction
Official progress
32.85%, as published by the Dubai Land Department
Planned completion
Jun 30, 2027
Construction start
Jan 1, 2025
Units
42
Buildings
1
Developer
Samana Star Real Estate Development
Master developer
Meydan Group
Community
Mohammed Bin Rashid Al Maktoum District 11, in DLD's area Wadi Al Safa 3
Escrow bank
First Abu Dhabi Bank
DLD project number
3329

The register describes it as: "B+G+5+R.The project designed to have a concrete structure and block with internal and external finishes."

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202632.85%Jun 30, 2027

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

42 off-plan sales in Rome 2 by SD have been registered with the Dubai Land Department, worth AED 80.8 million in all, the first on Feb 20, 2025 and the latest on Feb 17, 2026. The median price over the last 12 months was AED 18,152 per square meter (AED 1,686 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.