77.81%complete

Royal Manor

Royal Manor is a building project in Meydan Racecourse Community, Dubai, by Blue Coast Real Estate Development. The Dubai Land Department's register puts it at 77.81% complete, with planned completion on Dec 15, 2018.

Planned completion was Dec 15, 2018. Time since: 7 years 11 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 1855), which also shows the latest inspection date and photos.

Facts

Status
Past planned completion
Official progress
77.81%, as published by the Dubai Land Department
Planned completion
Dec 15, 2018
Construction start
Sep 15, 2016
Units
36
Buildings
1
Developer
Blue Coast Real Estate Development
Master developer
Meydan Group
Community
Meydan Racecourse Community, in DLD's area Nad Al Shiba First
Escrow bank
Dubai Islamic Bank
DLD project number
1855

The register describes it as: "B+G+4+R-Residential Building on Plot 6189033 at Nadd Al Shibba First (Meydan). 35 Units where 30 of which are one bedroom and 5 are two bedroom apartments.In addition, amenities like retail and swimming pool are available."

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202677.81%Dec 15, 2018

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

44 off-plan sales in Royal Manor have been registered with the Dubai Land Department, worth AED 33 million in all, the first on May 30, 2017 and the latest on Jul 29, 2024.

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.

More in Meydan Racecourse Community