4.68%complete

Sky Gate Tower

Sky Gate Tower is a building project in Jumeirah Village Triangle, Dubai, by Tiger Properties. The Dubai Land Department's register puts it at 4.68% complete, with planned completion on Feb 29, 2028.

Planned completion: Feb 29, 2028. Time left: 1 year 4 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 4120), which also shows the latest inspection date and photos.

Facts

Status
Under construction
Official progress
4.68%, as published by the Dubai Land Department
Planned completion
Feb 29, 2028
Construction start
Sep 15, 2025
Units
431
Buildings
1
Developer
Tiger Properties
Master developer
Nakheel .(P J S C)
Community
Jumeirah Village Triangle, in DLD's area Al Barsha South Fifth
Escrow bank
Abu Dhabi Commercial Bank
DLD project number
4120

The register describes it as: "3B+G+4P+3 Offices Floors + 33 Typical Floor + Roof"

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 20264.68%Feb 29, 2028

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

218 off-plan sales in Sky Gate Tower have been registered with the Dubai Land Department, worth AED 165 million in all, the first on Nov 24, 2025 and the latest on Oct 12, 2026. 7 of them in the last 90 days. The median price over the last 12 months was AED 17,043 per square meter (AED 1,583 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.