Ananda Residences
Ananda Residences is a building project in Motor City, Dubai, by Tiger Properties. The Dubai Land Department's register puts it at 3.2% complete, with planned completion on May 31, 2028.
Planned completion: May 31, 2028. Time left: 1 year 7 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3535), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 3.2%, as published by the Dubai Land Department
- Planned completion
- May 31, 2028
- Construction start
- Feb 1, 2025
- Units
- 1,027
- Buildings
- 2
- Developer
- Tiger Properties
- Master developer
- Union Properties
- Community
- Motor City, in DLD's area Al Hebiah First
- Escrow bank
- First Abu Dhabi Bank
- DLD project number
- 3535
The register describes it as: "Building 1 (Block A): G+53F+2MECH+R Building 2 ( Block B): G+53F+2MECH+R Shared Basement: 1B+G+R"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 3.2% | May 31, 2028 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
278 off-plan sales in Ananda Residences have been registered with the Dubai Land Department, worth AED 189 million in all, the first on Oct 10, 2025 and the latest on Oct 6, 2026. 8 of them in the last 90 days. The median price over the last 12 months was AED 14,234 per square meter (AED 1,322 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Motor City
- Sobha Orbis Motor City · Sobha 18.2%Planned completion Dec 31, 2028
- Sobha Solis Motor City · Sobha 17.92%Planned completion Dec 31, 2028
- Binghatti Skyterraces Motor City · Binghatti 0%Planned completion Oct 31, 2027
- Mirdad Motor City · Mirdad Real Estate Development 6.02%Planned completion Dec 31, 2028
- Takaya Motor City · Takaya Real Estate Development 15.62%Planned completion Dec 31, 2027
- Sierra by Iman Motor City · Iman 3.74%Planned completion Jun 30, 2029
More by Tiger
- Tiger Sky Tower Business Bay · Tiger 10.24%No planned date in the register
- Auresta Tower Jumeirah Village Circle · Tiger 4.44%Planned completion Dec 31, 2028
- Red Square Jumeirah Village Triangle · Tiger 26.71%No planned date in the register
- Guzel Towers Jumeirah Village Triangle · Tiger 7.3%Planned completion Dec 25, 2027
- Jade Tower Majan · Tiger 11%Planned completion Mar 31, 2027
- Sky Gate Tower Jumeirah Village Triangle · Tiger 4.68%Planned completion Feb 29, 2028