Tiger off-plan projects in Dubai
Tiger has 8 projects registered with the Dubai Land Department and not yet complete. Of its 7 projects finished since 2024, 1 finished by the planned date in the register.
Not yet complete
| Project | Community | Units | Planned completion | Progress |
|---|---|---|---|---|
| Jade Tower | Majan | 436 | Mar 31, 2027 | 11% |
| Guzel Towers | Jumeirah Village Triangle | 522 | Dec 25, 2027 | 7.3% |
| Sky Gate Tower | Jumeirah Village Triangle | 431 | Feb 29, 2028 | 4.68% |
| Ananda Residences | Motor City | 1,027 | May 31, 2028 | 3.2% |
| Auresta Tower | Jumeirah Village Circle | 840 | Dec 31, 2028 | 4.44% |
| Tiger Sky Tower | Business Bay | 849 | 10.24% | |
| Volga Tower | Jumeirah Village Triangle | 391 | 51.1% | |
| Red Square | Jumeirah Village Triangle | 835 | 26.71% |
Finished since 2024
| Project | Community | Planned | Completed |
|---|---|---|---|
| Altai Tower | Jumeirah Village Triangle | Jan 31, 2026 | Oct 21, 2026 |
| Lilium Tower | Jumeirah Village Triangle | Mar 31, 2026 | Oct 1, 2026 |
| Elbrus Tower | Jumeirah Village Triangle | Mar 31, 2026 | Sep 3, 2026 |
| Seslia Tower | Jumeirah Village Triangle | Dec 31, 2025 | Jul 22, 2026 |
| Neva Residences | Jumeirah Village Circle | Dec 31, 2025 | Mar 12, 2026 |
| CLOUD Tower | Jumeirah Village Triangle | Feb 28, 2025 | Oct 21, 2025 |
| Nobles | Business Bay | Aug 31, 2024 | Aug 31, 2024 |
The planned date is the one in the register at completion, which may itself have been revised.