Tiger off-plan projects in Dubai

Tiger has 8 projects registered with the Dubai Land Department and not yet complete. Of its 7 projects finished since 2024, 1 finished by the planned date in the register.

Not yet complete

ProjectCommunityUnitsPlanned completionProgress
Jade TowerMajan436Mar 31, 202711%
Guzel TowersJumeirah Village Triangle522Dec 25, 20277.3%
Sky Gate TowerJumeirah Village Triangle431Feb 29, 20284.68%
Ananda ResidencesMotor City1,027May 31, 20283.2%
Auresta TowerJumeirah Village Circle840Dec 31, 20284.44%
Tiger Sky TowerBusiness Bay84910.24%
Volga TowerJumeirah Village Triangle39151.1%
Red SquareJumeirah Village Triangle83526.71%

Finished since 2024

ProjectCommunityPlannedCompleted
Altai TowerJumeirah Village TriangleJan 31, 2026Oct 21, 2026
Lilium TowerJumeirah Village TriangleMar 31, 2026Oct 1, 2026
Elbrus TowerJumeirah Village TriangleMar 31, 2026Sep 3, 2026
Seslia TowerJumeirah Village TriangleDec 31, 2025Jul 22, 2026
Neva ResidencesJumeirah Village CircleDec 31, 2025Mar 12, 2026
CLOUD TowerJumeirah Village TriangleFeb 28, 2025Oct 21, 2025
NoblesBusiness BayAug 31, 2024Aug 31, 2024

The planned date is the one in the register at completion, which may itself have been revised.