Sobha Central
Sobha Central is a building project in DMCC-EZ2, Dubai, by Sobha. The Dubai Land Department's register puts it at 2.38% complete, with planned completion on Dec 31, 2031.
Planned completion: Dec 31, 2031. Time left: 5 years 2 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 4328), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 2.38%, as published by the Dubai Land Department
- Planned completion
- Dec 31, 2031
- Construction start
- Mar 31, 2026
- Units
- 2,169
- Buildings
- 3
- Developer
- Sobha
- Community
- DMCC-EZ2, in DLD's area Jabal Ali First
- Escrow bank
- Dubai Islamic Bank
- DLD project number
- 4328
The register describes it as: "The Proposed project is a mixed-use Residential, office, and Commercial complex consisting of two towers over a shared podium. Shared podium: 4 basements + Ground + 10 Podium Levels Building 5: 4 Basement + Ground + 89 Floors + 3 MECH+Roof Building 6: 4 Basement + Ground + 54 floors+1 MECH + Roof"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 2.38% | Dec 31, 2031 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
657 off-plan sales in Sobha Central have been registered with the Dubai Land Department, worth AED 1.85 billion in all, the first on Mar 26, 2026 and the latest on Nov 4, 2026. 136 of them in the last 90 days. The median price over the last 12 months was AED 34,821 per square meter (AED 3,235 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in DMCC-EZ2
More by Sobha
- Sobha One Ras Al Khor Industrial First · Sobha 86.21%No planned date in the register
- Sobha Orbis Motor City · Sobha 18.2%Planned completion Dec 31, 2028
- Skyvue Bukadra · Sobha 10.54%Planned completion Mar 31, 2030
- Sobha Solis Motor City · Sobha 17.92%Planned completion Dec 31, 2028
- Skyscape Bukadra · Sobha 38.27%Planned completion Dec 31, 2029
- Sobha Creek Vistas Heights Sobha Hartland · Sobha 91.53%No planned date in the register