Sobha Central Phase II
Sobha Central Phase II is a building project in DMCC-EZ2, Dubai, by Sobha. The Dubai Land Department's register puts it at 6.42% complete, with planned completion on Jun 30, 2030.
Planned completion: Jun 30, 2030. Time left: 3 years 8 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 4042), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 6.42%, as published by the Dubai Land Department
- Planned completion
- Jun 30, 2030
- Construction start
- Oct 1, 2025
- Units
- 2,143
- Buildings
- 2
- Developer
- Sobha
- Community
- DMCC-EZ2, in DLD's area Jabal Ali First
- Escrow bank
- Dubai Islamic Bank
- DLD project number
- 4042
The register describes it as: "The Proposed project is a mixed-use Residential, office, and Commercial complex consisting of two towers over a shared podium. Shared podium: 4 basements + Ground + 10 Podium Levels Building 1: 50 Floors + 1 MECH + Roof Building 2: 55 floors + 1 MECH + Roof"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 6.42% | Jun 30, 2030 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
808 off-plan sales in Sobha Central Phase II have been registered with the Dubai Land Department, worth AED 1.77 billion in all, the first on Oct 10, 2025 and the latest on Oct 30, 2026. 80 of them in the last 90 days. The median price over the last 12 months was AED 31,969 per square meter (AED 2,970 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in DMCC-EZ2
More by Sobha
- Sobha One Ras Al Khor Industrial First · Sobha 86.21%No planned date in the register
- Sobha Orbis Motor City · Sobha 18.2%Planned completion Dec 31, 2028
- Skyvue Bukadra · Sobha 10.54%Planned completion Mar 31, 2030
- Sobha Solis Motor City · Sobha 17.92%Planned completion Dec 31, 2028
- Skyscape Bukadra · Sobha 38.27%Planned completion Dec 31, 2029
- Sobha Creek Vistas Heights Sobha Hartland · Sobha 91.53%No planned date in the register