Sobha off-plan projects in Dubai

Sobha has 23 projects registered with the Dubai Land Department and not yet complete. Of its 8 projects finished since 2024, 6 finished by the planned date in the register.

Not yet complete

ProjectCommunityUnitsPlanned completionProgress
Verde by SobhaDMCC Master Community610Jun 30, 202785%
Sobha EstatesBukadra0Dec 31, 202768.49%
Sobha Seahaven Tower ADubai Harbour333Apr 30, 202837%
Elwood EstatesAl Yufrah 10Jun 30, 202814.35%
Sobha Seahaven Tower B & CDubai Harbour451Oct 31, 202840.2%
Sobha OrbisMotor City3,002Dec 31, 202818.2%
Sobha SolisMotor City2,351Dec 31, 202817.92%
SkyscapeBukadra1,852Dec 31, 202938.27%
The Element at Sobha OneRas Al Khor Industrial First401Dec 31, 202911.12%
SkyvueBukadra2,738Mar 31, 203010.54%
Sobha Central Phase IDMCC-EZ22,383Jun 30, 20307.08%
Sobha Central Phase IIDMCC-EZ22,143Jun 30, 20306.42%
Sobha CentralDMCC-EZ22,169Dec 31, 20312.38%
Sobha SkyParksBusiness Bay684Dec 31, 20320%
Sobha Creek Vistas HeightsSobha Hartland1,35491.53%
330 Riverside CrescentBukadra76767.81%
Sobha ReserveWadi Al Safa 21175.01%
Sobha OneRas Al Khor Industrial First3,05786.21%
310 Riverside CrescentBukadra91350.23%
360 Riverside CrescentBukadra91050.67%
340 Riverside CrescentBukadra76955.02%
350 Riverside CrescentBukadra75057.85%
320 Riverside CrescentBukadra63856.67%

Finished since 2024

ProjectCommunityPlannedCompleted
Sobha Hartland Waves OpulenceSobha HartlandSep 30, 2026Aug 6, 2026
Sobha Hartland - Crest GrandeSobha HartlandJun 30, 2026Apr 15, 2026
The S TowerSite AJun 30, 2025Feb 27, 2026
Sobha Hartland - the CrestSobha HartlandDec 31, 2025Dec 31, 2025
Sobha Creek Vistas GrandeSobha HartlandJul 31, 2025Jul 31, 2025
Sobha Hartland Waves GrandeSobha HartlandOct 31, 2023Oct 31, 2024
Sobha Hartland Villas Phase IIISobha HartlandJun 30, 2024Jun 30, 2024
Sobha Hartland WavesSobha HartlandMar 31, 2024Mar 31, 2024

The planned date is the one in the register at completion, which may itself have been revised.