Sunridge
Sunridge is a building project in Mina Rashid, Dubai, by Mina Rashid Properties. The Dubai Land Department's register puts it at 100% complete (completed).
Completed on Mar 17, 2026.
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2678), which also shows the latest inspection date and photos.
Facts
- Status
- Completed
- Official progress
- 100%, as published by the Dubai Land Department
- Construction start
- Sep 30, 2023
- Units
- 130
- Buildings
- 1
- Developer
- Mina Rashid Properties
- Community
- Mina Rashid, in DLD's area Madinat Dubai Almelaheyah
- Escrow bank
- Emirates Islamic Bank
- DLD project number
- 2678
The register describes it as: "B+G+5+R Residential, The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 100% |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
138 off-plan sales in Sunridge have been registered with the Dubai Land Department, worth AED 256 million in all, the first on Jul 11, 2023 and the latest on Jan 5, 2026. The median price over the last 12 months was AED 20,351 per square meter (AED 1,891 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Mina Rashid
- Marina Views Mina Rashid · Mina Rashid 7.09%Planned completion Dec 31, 2028
- Clearpoint Mina Rashid · Mina Rashid 45.05%No planned date in the register
- Seascape Mina Rashid · Mina Rashid 79.13%Planned completion Nov 30, 2026
- Baystar by VIDA Mina Rashid · Mina Rashid 6.3%Planned completion Dec 31, 2029
- Ocean Cove Mina Rashid · Mina Rashid 17.93%Planned completion Aug 31, 2028
- Ocean Point Mina Rashid · Mina Rashid 26.95%No planned date in the register
More by Mina Rashid
- Sera 1 Mina Rashid · Mina Rashid 0.04%Planned completion Nov 30, 2029
- Fior 1 Mina Rashid · Mina Rashid 0%Planned completion Jul 31, 2030
- Sera 2 Mina Rashid · Mina Rashid 0.04%Planned completion Nov 30, 2029
- Marina Place 2 Mina Rashid · Mina Rashid 1.52%Planned completion Dec 31, 2028
- Aurea Mina Rashid · Mina Rashid 0.22%Planned completion Jun 30, 2030
- Avonlea Mina Rashid · Mina Rashid 63.71%No planned date in the register