Sunset Bay Three by Imtiaz is a building project in Palm Deira, Dubai, by Imtiaz Sunset Real Estate Development. The Dubai Land Department's register puts it at 60.04% complete, with planned completion on Mar 20, 2027.
Planned completion: Mar 20, 2027. Time left: 4 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3604), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 60.04%, as published by the Dubai Land Department
- Planned completion
- Mar 20, 2027
- Construction start
- Mar 20, 2025
- Units
- 63
- Buildings
- 1
- Developer
- Imtiaz Sunset Real Estate Development
- Master developer
- Nakheel .(P J S C)
- Community
- Palm Deira
- Escrow bank
- First Abu Dhabi Bank
- DLD project number
- 3604
The register describes it as: "G+2P+8+R"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 60.04% | Mar 20, 2027 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
64 off-plan sales in Sunset Bay Three by Imtiaz have been registered with the Dubai Land Department, worth AED 153 million in all, the first on Jun 2, 2025 and the latest on Mar 31, 2026. The median price over the last 12 months was AED 21,033 per square meter (AED 1,954 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Palm Deira
- The Meriva Collection Palm Deira · Crestarc Developers 0.1%Planned completion Dec 31, 2031
- Hado by Beyond Palm Deira · Sandy Shores Real Estate L.L.C S.o.c 0.01%Planned completion Jun 30, 2029
- Ellington Sands I Palm Deira · Ellington 0.37%Planned completion Dec 31, 2028
- Ellington Sands II Palm Deira · Ellington 0.38%Planned completion Dec 31, 2028
- Bay Grove Residences C - Dubai Islands Palm Deira · Dubai Islands 7.29%Planned completion Apr 10, 2028
- Beach Residences Dubai Islands Palm Deira · Nakheel 28.8%No planned date in the register
More by Imtiaz
- Cove Living Residence by Imtiaz Dubai Land Residence Complex · Imtiaz 47.21%Planned completion Apr 15, 2027
- Cove Grand Residence by Imtiaz Dubai Land Residence Complex · Imtiaz 13.4%Planned completion Dec 15, 2027
- Cove Boulevard by Imtiaz Dubai Land Residence Complex · Imtiaz 10.45%Planned completion Oct 30, 2028
- Imtiaz Symphony Tower Bukadra · Imtiaz 6.3%Planned completion Jun 15, 2029
- Luxur Tower by Imtiaz Jumeirah Village Circle · Imtiaz 90.02%Planned completion Dec 15, 2026
- Le Blanc Residence by Imtiaz Dubai Land Residence Complex · Imtiaz 5.95%Planned completion Oct 15, 2028