100%complete

The Cove ll

The Cove ll is a building project in Dubai Creek Harbour, Dubai, by The Lagoons Phase One. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Dec 31, 2026.

Completed on May 6, 2026, against a planned date of Dec 31, 2026.

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2450), which also shows the latest inspection date and photos.

Facts

Status
Completed
Official progress
100%, as published by the Dubai Land Department
Planned completion
Dec 31, 2026
Construction start
Feb 10, 2023
Units
806
Buildings
13
Developer
The Lagoons Phase One
Community
Dubai Creek Harbour, in DLD's area Al Khairan First
Escrow bank
Dubai Islamic Bank
DLD project number
2450

The register describes it as: "Building 10 (F): 2B+G+7F+R Building 11 (E): 2B+G+7F+R Building 4 (K): G+22F+R Building 5 (I): 2B+G+7F+R Building 6 (L): G+7F+R Building 7 (H): 2B+G+8F+R Building 8 (G): 2B+G+8F+R Building 9 (M): G+19F+R Common 2B+G: 2B+G+R"

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 2026100%Dec 31, 2026

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

972 off-plan sales in The Cove ll have been registered with the Dubai Land Department, worth AED 3.01 billion in all, the first on Dec 5, 2022 and the latest on May 6, 2026. The median price over the last 12 months was AED 25,957 per square meter (AED 2,411 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.