The Valley-Nara
The Valley-Nara is a villa community in The Valley, Dubai, by Emaar Development. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Dec 30, 2024.
Completed on Dec 30, 2024, against a planned date of Dec 30, 2024.
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2274), which also shows the latest inspection date and photos.
Facts
- Status
- Completed
- Official progress
- 100%, as published by the Dubai Land Department
- Planned completion
- Dec 30, 2024
- Construction start
- Dec 1, 2021
- Villas
- 372
- Developer
- Emaar Development
- Community
- The Valley, in DLD's area Al Yufrah 1
- Escrow bank
- Commercial Bank of Dubai(psc)
- DLD project number
- 2274
The register describes it as: "Consisting of 372 Townhouses (G+1).The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 100% | Dec 30, 2024 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
526 off-plan sales in The Valley-Nara have been registered with the Dubai Land Department, worth AED 862 million in all, the first on Oct 5, 2021 and the latest on Dec 19, 2024.
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in The Valley
- The Valley - Rivana The Valley · Emaar 95.24%Planned completion Mar 31, 2027
- The Valley - Nima The Valley · Emaar 80.02%No planned date in the register
- The Valley - Alana The Valley · Emaar 81.56%No planned date in the register
- The Valley - Farm Gardens 2 The Valley · Emaar 59.08%No planned date in the register
- The Valley - Velora The Valley · Emaar 50.07%Planned completion Aug 31, 2028
- The Valley - Venera The Valley · Emaar 51.7%Planned completion Sep 30, 2028
More by Emaar
- The St. Regis Residences, Downtown Dubai DownTown Dubai · Emaar 76.05%Planned completion Dec 25, 2026
- Palace by the Beach Dubai Harbour · Emaar 0%Planned completion Nov 30, 2031
- Avarra by Palace Business Bay · Emaar 0.08%Planned completion Jun 30, 2031
- Bayview Dubai Harbour · Emaar 63.02%Planned completion Jul 31, 2028
- Seapoint Dubai Harbour · Emaar 36.78%Planned completion Mar 31, 2028
- Golf Point Dubai World Central · Emaar 4.78%Planned completion Oct 31, 2028