100%complete

The Valley - Talia

The Valley - Talia is a villa community in The Valley, Dubai, by Emaar Development. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Mar 31, 2025.

Completed on Mar 31, 2025, against a planned date of Mar 31, 2025.

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2303), which also shows the latest inspection date and photos.

Facts

Status
Completed
Official progress
100%, as published by the Dubai Land Department
Planned completion
Mar 31, 2025
Construction start
Feb 20, 2022
Villas
330
Developer
Emaar Development
Community
The Valley, in DLD's area Al Yufrah 1
Escrow bank
Emirates NBD Bank
DLD project number
2303

The register describes it as: "Residential Development Consisting of 330 Townhouses (G+1).The project designed to have a concrete structure and block with internal and external finishes."

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 2026100%Mar 31, 2025

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

442 off-plan sales in The Valley - Talia have been registered with the Dubai Land Department, worth AED 778 million in all, the first on Feb 2, 2022 and the latest on Jan 14, 2025.

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.