Vedaire Residences is a building project in Meydan Racecourse Community, Dubai, by Elton Real Estate Development. The Dubai Land Department's register puts it at 0% complete (not started), with planned completion on Mar 31, 2028.
Planned completion: Mar 31, 2028. Time left: 1 year 5 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3599), which also shows the latest inspection date and photos.
Facts
- Status
- Not started
- Official progress
- 0%, as published by the Dubai Land Department
- Planned completion
- Mar 31, 2028
- Construction start
- Oct 15, 2025
- Units
- 46
- Buildings
- 1
- Developer
- Elton Real Estate Development
- Master developer
- Meydan Group
- Community
- Meydan Racecourse Community, in DLD's area Nad Al Shiba First
- DLD project number
- 3599
The register describes it as: "Residential Building (B+G+5)"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 0% | Mar 31, 2028 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
19 off-plan sales in Vedaire Residences have been registered with the Dubai Land Department, worth AED 33.7 million in all, the first on Sep 1, 2025 and the latest on Nov 5, 2026. 8 of them in the last 90 days. The median price over the last 12 months was AED 21,852 per square meter (AED 2,030 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Meydan Racecourse Community
- Maybach Six Meydan Racecourse Community · Binghatti 0%Planned completion Aug 31, 2027
- Maybach Ultimate Luxury Meydan Racecourse Community · Binghatti 0%Planned completion Aug 31, 2027
- Project Maybach Meydan Racecourse Community · Binghatti 0%Planned completion Jun 30, 2027
- Tonino Lamborghini Residences Meydan Racecourse Community · Gulf Land 60%Planned completion Dec 31, 2026
- Emerge Residences Meydan Racecourse Community · N A A S Real Estate Development 21.13%Planned completion Nov 1, 2027
- Saddlewood Park Meydan Racecourse Community · Mak Developers 12.45%Planned completion Sep 30, 2027