VELA by OMNIYAT is a building project in Business Bay, Dubai, by Downtown Creek Real Estate Development. The Dubai Land Department's register puts it at 50.03% complete.
The register gives no planned completion date for this project.
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2653), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 50.03%, as published by the Dubai Land Department
- Construction start
- Jun 1, 2023
- Units
- 39
- Buildings
- 1
- Developer
- Downtown Creek Real Estate Development
- Master developer
- Business Bay
- Community
- Business Bay
- Escrow bank
- Abu Dhabi Commercial Bank
- DLD project number
- 2653
The register describes it as: "Proposed Tower 4B+G+30 floors + Retail B03 1 unit.The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 50.03% |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
27 off-plan sales in VELA by OMNIYAT have been registered with the Dubai Land Department, worth AED 1.11 billion in all, the first on Nov 10, 2023 and the latest on Nov 3, 2026. 1 of them in the last 90 days. The median price over the last 12 months was AED 72,580 per square meter (AED 6,743 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Business Bay
- Binghatti Skyrise Business Bay · Binghatti 35.89%Planned completion Dec 31, 2026
- Al Habtoor Tower Business Bay · Al Habtoor 90.01%Planned completion Dec 31, 2026
- Binghatti Aquarise Business Bay · Binghatti 21.04%Planned Oct 31, 2026, 7 days ago
- Bayz 101 by Danube Business Bay · Danube 10%No planned date in the register
- Aykon City 3 Business Bay · Damac 31.35%Planned completion Dec 30, 2027
- Bayz 102 by Danube Business Bay · Danube 6.52%Planned completion Dec 31, 2029