Address the Bay
Address the Bay is a building project in Dubai Harbour, Dubai, by Emaar Development. The Dubai Land Department's register puts it at 70.08% complete, with planned completion on Dec 31, 2026.
Planned completion: Dec 31, 2026. Time left: 2 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2397), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 70.08%, as published by the Dubai Land Department
- Planned completion
- Dec 31, 2026
- Construction start
- Nov 10, 2022
- Units
- 448
- Buildings
- 1
- Developer
- Emaar Development
- Community
- Dubai Harbour, in DLD's area Marsa Dubai
- Escrow bank
- Commercial Bank of Dubai(psc)
- DLD project number
- 2397
The register describes it as: "2B+G+1M+6P+49F+5PH+1LR+R ,Residential-Apartment + Hospitality-Hotel. The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 70.08% | Dec 31, 2026 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
631 off-plan sales in Address the Bay have been registered with the Dubai Land Department, worth AED 3.44 billion in all, the first on Jul 19, 2022 and the latest on Nov 3, 2026. 10 of them in the last 90 days. The median price over the last 12 months was AED 43,211 per square meter (AED 4,014 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Dubai Harbour
- Damac Bay Dubai Harbour · Damac 33.76%Planned completion Jan 15, 2027
- Palace by the Beach Dubai Harbour · Emaar 0%Planned completion Nov 30, 2031
- Bayview Dubai Harbour · Emaar 63.02%Planned completion Jul 31, 2028
- Seapoint Dubai Harbour · Emaar 36.78%Planned completion Mar 31, 2028
- Damac Bay 2 Dubai Harbour · Damac 30.3%No planned date in the register
- W Residences at Dubai Harbour Dubai Harbour · Arada 3.99%Planned completion Dec 31, 2028
More by Emaar
- The St. Regis Residences, Downtown Dubai DownTown Dubai · Emaar 76.05%Planned completion Dec 25, 2026
- Avarra by Palace Business Bay · Emaar 0.08%Planned completion Jun 30, 2031
- Golf Point Dubai World Central · Emaar 4.78%Planned completion Oct 31, 2028
- Maysan Al Yelayiss 2 · Emaar 36.7%Planned Jul 1, 2016, 10 years 4 months ago
- Marina Shores Dubai Marina · Emaar 87.18%Planned completion Dec 31, 2026
- Golf Vale Dubai World Central · Emaar 0%Planned completion Mar 31, 2030