Off-plan projects in Motor City
13 projects in Motor City are registered and not yet complete, 2 of them past the planned completion date, according to the Dubai Land Department.
Not yet complete
| Project | Developer | Units | Planned completion | Progress |
|---|---|---|---|---|
| The Community Motor City | Aqua | 433 | Oct 31, 2025 | 95.06% |
| Monarch | Zane Developments | 47 | Oct 1, 2026 | 32.3% |
| Capital One | The Circuit Real Estate Development | 257 | Feb 9, 2027 | 20.02% |
| Sobha Orbis | Sobha | 3,002 | Dec 31, 2028 | 18.2% |
| Sobha Solis | Sobha | 2,351 | Dec 31, 2028 | 17.92% |
| Takaya | Takaya Real Estate Development | 822 | Dec 31, 2027 | 15.62% |
| Velos Residence | City View Urban Real Estate Development | 413 | Oct 31, 2028 | 6.6% |
| Mirdad | Mirdad Real Estate Development | 1,114 | Dec 31, 2028 | 6.02% |
| 15 Cascade | Iman | 442 | Sep 30, 2028 | 5.5% |
| Sierra by Iman | Iman | 598 | Jun 30, 2029 | 3.74% |
| Ananda Residences | Tiger | 1,027 | May 31, 2028 | 3.2% |
| Beverly Grande | H M B Homes Real Estate Development | 296 | Dec 31, 2027 | 0.47% |
| Binghatti Skyterraces | Binghatti | 1,886 | Oct 31, 2027 | 0% |