Off-plan projects in Wadi Al Safa 4

9 projects in Wadi Al Safa 4 are registered and not yet complete, 1 of them past the planned completion date, according to the Dubai Land Department.

Not yet complete

ProjectDeveloperUnitsPlanned completionProgress
California VillageGfh Real Estate0Jul 15, 202595.07%
CiliaMajid Al Futtaim54643.82%
SerraMajid Al Futtaim53542.05%
LacinaMajid Al Futtaim324Dec 30, 202720.81%
DistriktMajid Al Futtaim550Sep 30, 20288.39%
California ResidencesGfh Real Estate372Apr 1, 20281.74%
Capria WestMajid Al Futtaim714May 8, 20291.23%
Capria EastMajid Al Futtaim553May 15, 20290.94%
Azizi Milan 9Azizi1,180May 30, 20270%