Majid Al Futtaim off-plan projects in Dubai
Majid Al Futtaim has 12 projects registered with the Dubai Land Department and not yet complete, 3 past the planned completion date. Of its 2 projects finished since 2024, 0 finished by the planned date in the register.
Registered under 2 company names: Majid Al Futtaim Tilal Al Ghaf Phase A, Majid Al Futtaim Ghaf Woods.
Not yet complete
| Project | Community | Units | Planned completion | Progress |
|---|---|---|---|---|
| Elysian Mansions | Tilal Al Ghaf | 0 | Mar 31, 2025 | 95.02% |
| Alaya | Tilal Al Ghaf | 0 | Jul 20, 2026 | 91.45% |
| LANAI Island | Tilal Al Ghaf | 0 | Sep 30, 2026 | 60.56% |
| Lacina | Wadi Al Safa 4 | 324 | Dec 30, 2027 | 20.81% |
| Distrikt | Wadi Al Safa 4 | 550 | Sep 30, 2028 | 8.39% |
| Capria West | Wadi Al Safa 4 | 714 | May 8, 2029 | 1.23% |
| Capria East | Wadi Al Safa 4 | 553 | May 15, 2029 | 0.94% |
| Serenity Mansions | Tilal Al Ghaf | 0 | 32.4% | |
| Plagette 32 | Tilal Al Ghaf | 0 | 60.57% | |
| Amara | Tilal Al Ghaf | 0 | 70.8% | |
| Cilia | Wadi Al Safa 4 | 546 | 43.82% | |
| Serra | Wadi Al Safa 4 | 535 | 42.05% |
Finished since 2024
| Project | Community | Planned | Completed |
|---|---|---|---|
| Harmony | Tilal Al Ghaf | Jun 30, 2024 | Dec 30, 2025 |
| Aura | Tilal Al Ghaf | Aug 31, 2024 | Oct 13, 2025 |
The planned date is the one in the register at completion, which may itself have been revised.