Lacina
Lacina is a building project in Wadi Al Safa 4, Dubai, by Majid Al Futtaim Ghaf Woods. The Dubai Land Department's register puts it at 20.81% complete, with planned completion on Dec 30, 2027.
Planned completion: Dec 30, 2027. Time left: 1 year 2 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3336), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 20.81%, as published by the Dubai Land Department
- Planned completion
- Dec 30, 2027
- Construction start
- Dec 1, 2024
- Units
- 324
- Buildings
- 3
- Developer
- Majid Al Futtaim Ghaf Woods
- Master developer
- Majid Al Futtaim Emirati Communities Operation
- Community
- Wadi Al Safa 4
- Escrow bank
- Emirates NBD Bank
- DLD project number
- 3336
The register describes it as: "The project contains three buildings shared on ground and podium floors.he project designed to have a concrete structure and block with internal and external finishes. Building 01: Consist of G+P+l0 floors and includes 125 units (79 apartments lBR and 46 apartments 2BR) Building 02: Consist of G+P+ll floors and includes 74 units (48 apartments 2BR and 26 apartments 3BR) Building 03: Consist of G+P+l0 floors and includes 125 units (79 apartments lBR and 46 apartments 2BR)"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 20.81% | Dec 30, 2027 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
330 off-plan sales in Lacina have been registered with the Dubai Land Department, worth AED 689 million in all, the first on Jan 7, 2025 and the latest on Apr 30, 2026. The median price over the last 12 months was AED 21,078 per square meter (AED 1,958 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Wadi Al Safa 4
- Azizi Milan 9 Wadi Al Safa 4 · Azizi 0%Planned completion May 30, 2027
- Capria West Wadi Al Safa 4 · Majid Al Futtaim 1.23%Planned completion May 8, 2029
- Capria East Wadi Al Safa 4 · Majid Al Futtaim 0.94%Planned completion May 15, 2029
- Distrikt Wadi Al Safa 4 · Majid Al Futtaim 8.39%Planned completion Sep 30, 2028
- Cilia Wadi Al Safa 4 · Majid Al Futtaim 43.82%No planned date in the register
- Serra Wadi Al Safa 4 · Majid Al Futtaim 42.05%No planned date in the register
More by Majid Al Futtaim
- Elysian Mansions Tilal Al Ghaf · Majid Al Futtaim 95.02%Planned Mar 31, 2025, 1 year 7 months ago
- Alaya Tilal Al Ghaf · Majid Al Futtaim 91.45%Planned Jul 20, 2026, 4 months ago
- LANAI Island Tilal Al Ghaf · Majid Al Futtaim 60.56%Planned Sep 30, 2026, 38 days ago
- Serenity Mansions Tilal Al Ghaf · Majid Al Futtaim 32.4%No planned date in the register
- Plagette 32 Tilal Al Ghaf · Majid Al Futtaim 60.57%No planned date in the register
- Amara Tilal Al Ghaf · Majid Al Futtaim 70.8%No planned date in the register