Azha Downtown Residences is a building project in DownTown Dubai, Dubai, by Azha Downtown Residences. The Dubai Land Department's register puts it at 26.96% complete, with planned completion on Aug 31, 2027.
Planned completion: Aug 31, 2027. Time left: 10 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3129), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 26.96%, as published by the Dubai Land Department
- Planned completion
- Aug 31, 2027
- Construction start
- Aug 15, 2024
- Units
- 73
- Buildings
- 1
- Developer
- Azha Downtown Residences
- Master developer
- Emaar Development
- Community
- DownTown Dubai, in DLD's area Burj Khalifa
- Escrow bank
- Commercial Bank of Dubai(psc)
- DLD project number
- 3129
The register describes it as: "G + M + 2P + 11.The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 26.96% | Aug 31, 2027 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
53 off-plan sales in Azha Downtown Residences have been registered with the Dubai Land Department, worth AED 202 million in all, the first on Oct 7, 2024 and the latest on Jun 12, 2026. The median price over the last 12 months was AED 26,394 per square meter (AED 2,452 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in DownTown Dubai
- The St. Regis Residences, Downtown Dubai DownTown Dubai · Emaar 76.05%Planned completion Dec 25, 2026
- Binghatti Skyblade DownTown Dubai · Binghatti 17.06%Planned completion Nov 30, 2027
- One Residence DownTown Dubai · Ginco Properties 6.33%Planned completion Mar 31, 2027
- City Center Residences DownTown Dubai · Dar Global Properties 72.3%Planned Sep 30, 2026, 38 days ago
- ROVE HOME RESIDENCES by IRTH DownTown Dubai · Irth Development 62.69%Planned Apr 30, 2026, 6 months ago
- Euphoric Residences DownTown Dubai · East & West Properties 8.3%Planned completion Dec 31, 2027