72.3%complete

City Center Residences

City Center Residences is a building project in DownTown Dubai, Dubai, by Dar Global Properties. The Dubai Land Department's register puts it at 72.3% complete, with planned completion on Sep 30, 2026.

Planned completion was Sep 30, 2026. Time since: 38 days

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2359), which also shows the latest inspection date and photos.

Facts

Status
Past planned completion
Official progress
72.3%, as published by the Dubai Land Department
Planned completion
Sep 30, 2026
Construction start
May 1, 2022
Units
384
Buildings
1
Developer
Dar Global Properties
Master developer
Emaar Development
Community
DownTown Dubai, in DLD's area Burj Khalifa
Escrow bank
Emirates NBD Bank
DLD project number
2359

The register describes it as: "Tower consists of 1B+G+4P+49F+1MECH+R+4UR Floors (Residential Commercial) with external and internal finishes."

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202672.3%Sep 30, 2026

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

557 off-plan sales in City Center Residences have been registered with the Dubai Land Department, worth AED 1.55 billion in all, the first on May 26, 2022 and the latest on Oct 15, 2026. 6 of them in the last 90 days. The median price over the last 12 months was AED 29,152 per square meter (AED 2,708 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.