100%complete

Azizi Riviera 38

Azizi Riviera 38 is a building project in Meydan One Community, Dubai, by Azizi Developments. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Jan 18, 2024.

Completed on Jan 18, 2024, against a planned date of Jan 18, 2024.

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2051), which also shows the latest inspection date and photos.

Facts

Status
Completed
Official progress
100%, as published by the Dubai Land Department
Planned completion
Jan 18, 2024
Construction start
Jun 1, 2018
Units
161
Buildings
1
Developer
Azizi Developments
Master developer
Meydan Group
Community
Meydan One Community, in DLD's area Al Merkadh
Escrow bank
Abu Dhabi Commercial Bank
DLD project number
2051

The register describes it as: "1 Building, Residential+ Retail+ 2B+ G+ 10 Floors+ Roof with internal and external finishes."

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 2026100%Jan 18, 2024

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

152 off-plan sales in Azizi Riviera 38 have been registered with the Dubai Land Department, worth AED 143 million in all, the first on Sep 27, 2018 and the latest on Jan 7, 2025.

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.