74.56%complete

Azizi Riviera 68

Azizi Riviera 68 is a building project in Meydan One Community, Dubai, by Azizi Developments. The Dubai Land Department's register puts it at 74.56% complete, with planned completion on May 30, 2027.

Planned completion: May 30, 2027. Time left: 7 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 3795), which also shows the latest inspection date and photos.

Facts

Status
Under construction
Official progress
74.56%, as published by the Dubai Land Department
Planned completion
May 30, 2027
Construction start
May 23, 2025
Units
112
Buildings
1
Developer
Azizi Developments
Master developer
Meydan Group
Community
Meydan One Community, in DLD's area Al Merkadh
Escrow bank
Abu Dhabi Commercial Bank
DLD project number
3795

The register describes it as: "PROPOSED RESIDENTIAL BUILDING (2B+G+8+ROOF)"

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202674.56%May 30, 2027

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

79 off-plan sales in Azizi Riviera 68 have been registered with the Dubai Land Department, worth AED 123 million in all, the first on Jul 7, 2025 and the latest on Nov 4, 2026. 14 of them in the last 90 days. The median price over the last 12 months was AED 21,222 per square meter (AED 1,972 per square foot).

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.