Solara Tower Dubai
Solara Tower Dubai is a building project in DownTown Dubai, Dubai, by S O L Properties Development. The Dubai Land Department's register puts it at 20.73% complete, with planned completion on Aug 15, 2027.
Planned completion: Aug 15, 2027. Time left: 9 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2928), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 20.73%, as published by the Dubai Land Department
- Planned completion
- Aug 15, 2027
- Construction start
- Aug 1, 2024
- Units
- 231
- Buildings
- 1
- Developer
- S O L Properties Development
- Master developer
- Emaar Development
- Community
- DownTown Dubai, in DLD's area Burj Khalifa
- Escrow bank
- Emirates NBD Bank
- DLD project number
- 2928
The register describes it as: "Building Consists of 4B+G+M+3P+51 Floors.The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 20.73% | Aug 15, 2027 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
165 off-plan sales in Solara Tower Dubai have been registered with the Dubai Land Department, worth AED 1.5 billion in all, the first on Dec 13, 2024 and the latest on Oct 22, 2026. 4 of them in the last 90 days. The median price over the last 12 months was AED 40,261 per square meter (AED 3,740 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in DownTown Dubai
- The St. Regis Residences, Downtown Dubai DownTown Dubai · Emaar 76.05%Planned completion Dec 25, 2026
- Binghatti Skyblade DownTown Dubai · Binghatti 17.06%Planned completion Nov 30, 2027
- One Residence DownTown Dubai · Ginco Properties 6.33%Planned completion Mar 31, 2027
- City Center Residences DownTown Dubai · Dar Global Properties 72.3%Planned Sep 30, 2026, 38 days ago
- ROVE HOME RESIDENCES by IRTH DownTown Dubai · Irth Development 62.69%Planned Apr 30, 2026, 6 months ago
- Euphoric Residences DownTown Dubai · East & West Properties 8.3%Planned completion Dec 31, 2027
More by S O L Properties Development
- Sol Levante Jumeirah Village Triangle · S O L Properties Development 7.19%Planned completion Sep 15, 2028
- Sol Luxe Trade Center First · S O L Properties Development 1.99%Planned completion Mar 15, 2029
- Sol Terra Casa I Jumeirah Village Circle · S O L Properties Development 0%Planned completion Jun 15, 2028