95.02%complete

Elysian Mansions

Elysian Mansions is a villa project in Tilal Al Ghaf, Dubai, by Majid Al Futtaim Tilal Al Ghaf Phase A. The Dubai Land Department's register puts it at 95.02% complete, with planned completion on Mar 31, 2025.

Planned completion was Mar 31, 2025. Time since: 1 year 7 months

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2054), which also shows the latest inspection date and photos.

Facts

Status
Past planned completion
Official progress
95.02%, as published by the Dubai Land Department
Planned completion
Mar 31, 2025
Construction start
Sep 1, 2018
Developer
Majid Al Futtaim Tilal Al Ghaf Phase A
Master developer
Majid Al Futtaim Emirati Communities Operation
Community
Tilal Al Ghaf, in DLD's area Al Hebiah Fourth
Escrow bank
Emirates NBD Bank
DLD project number
2054

The register describes it as: "97 x B+G+2 Villas.The project designed to have a concrete structure and block with internal and external finishes."

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202695.02%Mar 31, 2025

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

More in Tilal Al Ghaf

More by Majid Al Futtaim