60.56%complete

LANAI Island

LANAI Island is a villa project in Tilal Al Ghaf, Dubai, by Majid Al Futtaim Tilal Al Ghaf Phase A. The Dubai Land Department's register puts it at 60.56% complete, with planned completion on Sep 30, 2026.

Planned completion was Sep 30, 2026. Time since: 38 days

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2498), which also shows the latest inspection date and photos.

Facts

Status
Past planned completion
Official progress
60.56%, as published by the Dubai Land Department
Planned completion
Sep 30, 2026
Construction start
Apr 30, 2023
Developer
Majid Al Futtaim Tilal Al Ghaf Phase A
Master developer
Majid Al Futtaim Emirati Communities Operation
Community
Tilal Al Ghaf, in DLD's area Al Hebiah Fourth
Escrow bank
Emirates NBD Bank
DLD project number
2498

The register describes it as: "27 Villas (B+G+1+R), (Old: - 13 Villas (B+G+1+R) Villas, The project designed to have a concrete structure and block with internal and external finishes."

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 202660.56%Sep 30, 2026

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.