Inaura Hotels & Residences
Inaura Hotels & Residences is a building project in DownTown Dubai, Dubai, by Arada Developments L.L.C S.o.c. The Dubai Land Department's register puts it at 1.32% complete, with planned completion on Jun 14, 2030.
Planned completion: Jun 14, 2030. Time left: 3 years 7 months
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 4226), which also shows the latest inspection date and photos.
Facts
- Status
- Under construction
- Official progress
- 1.32%, as published by the Dubai Land Department
- Planned completion
- Jun 14, 2030
- Construction start
- Dec 15, 2026
- Units
- 119
- Buildings
- 1
- Developer
- Arada Developments L.L.C S.o.c
- Master developer
- Emaar Development
- Community
- DownTown Dubai, in DLD's area Burj Khalifa
- Escrow bank
- Dubai Islamic Bank
- DLD project number
- 4226
The register describes it as: "The project "Inaura Hotels & Residences" project, by ARADA DEVELOPMENTS L.L.C S.O.C located on Plot No. 531 at Burj Khalifa (3450423), Dubai, UAE. The project is a Residential and Hotel development with 114 no. Residential Units and total 101 no. Hotel Keys"
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 1.32% | Jun 14, 2030 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
36 off-plan sales in Inaura Hotels & Residences have been registered with the Dubai Land Department, worth AED 287 million in all, the first on Mar 30, 2026 and the latest on Oct 28, 2026. 15 of them in the last 90 days. The median price over the last 12 months was AED 53,640 per square meter (AED 4,983 per square foot).
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in DownTown Dubai
- The St. Regis Residences, Downtown Dubai DownTown Dubai · Emaar 76.05%Planned completion Dec 25, 2026
- Binghatti Skyblade DownTown Dubai · Binghatti 17.06%Planned completion Nov 30, 2027
- One Residence DownTown Dubai · Ginco Properties 6.33%Planned completion Mar 31, 2027
- City Center Residences DownTown Dubai · Dar Global Properties 72.3%Planned Sep 30, 2026, 38 days ago
- ROVE HOME RESIDENCES by IRTH DownTown Dubai · Irth Development 62.69%Planned Apr 30, 2026, 6 months ago
- Euphoric Residences DownTown Dubai · East & West Properties 8.3%Planned completion Dec 31, 2027
More by Arada
- Akala Hotels and Residences Dubai International Financial Center · Arada 1.88%Planned completion Oct 31, 2029
- W Residences at Dubai Harbour Dubai Harbour · Arada 3.99%Planned completion Dec 31, 2028
- Armani Beach Residences at Palm Jumeirah Palm Jumeirah · Arada 10.17%Planned completion Dec 31, 2027
- Jouri Hills Jumeirah Golf Estates · Arada 78.47%Planned Jun 30, 2026, 4 months ago