Royal Regency
Royal Regency is a building project in Business Bay, Dubai, by Alseeb Real Estate Development. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Feb 28, 2026.
Completed on Nov 5, 2025, against a planned date of Feb 28, 2026.
Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2654), which also shows the latest inspection date and photos.
Facts
- Status
- Completed
- Official progress
- 100%, as published by the Dubai Land Department
- Planned completion
- Feb 28, 2026
- Construction start
- Nov 1, 2022
- Units
- 165
- Buildings
- 1
- Developer
- Alseeb Real Estate Development
- Master developer
- Business Bay
- Community
- Business Bay
- Escrow bank
- Sharjah Islamic Bank
- DLD project number
- 2654
The register describes it as: "2B+G+18F+R (Last two floors are penthouse) Residential, The project designed to have a concrete structure and block with internal and external finishes."
Progress as the register reported it
| Since | Progress | Planned completion |
|---|---|---|
| Oct 29, 2026 | 100% | Feb 28, 2026 |
Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.
Off-plan sales registered
152 off-plan sales in Royal Regency have been registered with the Dubai Land Department, worth AED 319 million in all, the first on Jan 25, 2024 and the latest on Nov 3, 2025.
Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.
More in Business Bay
- Binghatti Skyrise Business Bay · Binghatti 35.89%Planned completion Dec 31, 2026
- Al Habtoor Tower Business Bay · Al Habtoor 90.01%Planned completion Dec 31, 2026
- Binghatti Aquarise Business Bay · Binghatti 21.04%Planned Oct 31, 2026, 7 days ago
- Bayz 101 by Danube Business Bay · Danube 10%No planned date in the register
- Aykon City 3 Business Bay · Damac 31.35%Planned completion Dec 30, 2027
- Bayz 102 by Danube Business Bay · Danube 6.52%Planned completion Dec 31, 2029