100%complete

Aura

Aura is a villa community in Tilal Al Ghaf, Dubai, by Majid Al Futtaim Tilal Al Ghaf Phase A. The Dubai Land Department's register puts it at 100% complete (completed), with planned completion on Aug 31, 2024.

Completed on Oct 13, 2025, against a planned date of Aug 31, 2024.

Register read Nov 7, 2026. Check it on the Dubai Land Department's site (search for project 2259), which also shows the latest inspection date and photos.

Facts

Status
Completed
Official progress
100%, as published by the Dubai Land Department
Planned completion
Aug 31, 2024
Construction start
Nov 6, 2021
Villas
808
Developer
Majid Al Futtaim Tilal Al Ghaf Phase A
Master developer
Majid Al Futtaim Emirati Communities Operation
Community
Tilal Al Ghaf, in DLD's area Al Hebiah Fourth
Escrow bank
Emirates NBD Bank
DLD project number
2259

The register describes it as: "808 Townhouses,(G+1+R) & (G+2+R).The project designed to have a concrete structure and block with internal and external finishes."

Progress as the register reported it

SinceProgressPlanned completion
Oct 29, 2026100%Aug 31, 2024

Each row is a value the register held from the date we first saw it. Offplan.tv has read the register daily since Oct 29, 2026, so earlier progress is not shown.

Off-plan sales registered

1,246 off-plan sales in Aura have been registered with the Dubai Land Department, worth AED 3.53 billion in all, the first on Jul 19, 2021 and the latest on Aug 20, 2025.

Sales registered through Nov 5, 2026, from DLD's transactions on data.dubai.